Main Line Replacement Capital Improvement Project Update (updated August 18, 2011)
In Progress:
Final paving of South Park Drive and Endicott Circle will begin on Monday, August 22nd and is expected to be completed by September 2nd. The final raising of meter boxes to grade and other finishing touches will be completed immediately following. The project is expected to be 100% completed by mid-September, 2011.
Completed:
Mainline and valve replacement has been completed, as well as fire hydrant installation. Attached new services have been installed and the final tie-in on Glendale Ct. has been completed.